Mission Bhagheeratha (Grid)

MISSION BHAGIRATHA – GRID

PALAIR WARANGAL SEGMENT

The Government of Telangana has taken up the water Grid program (Mission Bhaghiratha Program) as a flag ship item to provide safe drinking water to all rural and urban people at 100 lpcd to rural households and 135 lpcd in municipality areas.

As a part of Programme Palair segment is proposed in Mahabubabad District 14 mandal’s of Dornakal, Mahabubabad, Palakurthy and Mulugu constituencies also 4 Municipalities (ULB) i.e, Mahabubabad, Dornakal, Maripeda and Thorrur from Palair reservoir in Khammam District as a source.

Segment Details:

Name of the work

:

Providing Drinking water supply to 17 Mandals in Warangal District and 1 Mandal in Khammam District including 10 Years O&M under TDWSP

Administrative Sanction

:

Rs 1700.00 Crs

Executing Agencies 

:

Civil Works      –  M/s MEIL

EM Works        –  M/s NCCL

CPWS Scheme –  M/s Challa Infra

Others               – M/s Aditya Infra,

                           – M/s Rajakomuraiah, 

                           – M/s Paidaiah

Raw Water Source

:

Palair Reservoir

 

Intake Well:

Intake well at Palair reservoir of Khammam District is being executed under Khammam segment scope with provision of pumping of raw water to Warangal palair segment from it.

Power and Pump sets at Intake well:

The pump sets of 724 HP each (4 working and 2 stand by) provided at Palair Intake well and the power requirement is 2.16 MW for raw water pumping.

            For clear water pumping 46 working and 28 Stand by pump sets were provided at intermediate pumping stations with power requirement 5.804 MW

Pumping Main:

Raw water pumping main of 1700 mm dia from Intake well at Palair reservoir to 170MLD WTP at Abbaipalem total length is 21.25 Km is completed and commissioned.

Awareness Program:

 Awareness programs are also being conducting with the Mandal level public representatives and Government officials to create the awareness about the usage of the Mission Bhagiratha drinking water. As part of this, awareness was conducted on Dec 30th 2019 at Maripeda  Abbaipalem (WTP) village, for Thorrur, Peddavangara, Rayaparthy Mandals along with all the public representatives and mandal level officials.

Habitation Coverage:  

Palair Warangal Segment is covering 14 Mandals of Mahabubabad District including 1 Old and 3 New ULBs and for the remaining habitations bulk water is being supplied from Godavari – Dummugudem and HMWSS segments. Constituency wise habitation coverage is given below:

S.No

Constituency

Mandal

Total Rural Habs

ULB Merged Habs

Total Habs

1

Dornakal

Chinnagudur

22

0

22

2

Maripeda

124

22

146

3

Narsimhulapet

75

0

75

4

Dornakal

84

11

95

5

Korivi

119

0

119

6

Danthalapalle

30

0

30

Dornakal Constituency Sub Total

454

33

487

6

Mahabubabad

Danthalapalle

3

0

3

7

Mahabubabad

105

29

134

8

Nellikudur

118

0

118

9

Kesamudram

125

0

125

10

Gudur

155

0

155

Mahabubabad Constituency Sub Total

506

29

535

11

Palakurthy

Peddavangara

15

0

15

12

Thorrur

74

6

80

Palakurthy Constituency Sub Total

89

6

95

14

Mulugu

Gangaram

30

0

30

15

Kothaguda

59

0

59

Mulugu Constituency Sub Total

89

0

89

Mahabubabad District Habs Total

1138

68

1206

 

Structures:

  • At WTP head quarters: – 170 MLD Water Treatment Plant
  1.                 30000 KL Clear Water Sump and Pump house
  2.                 GLBRs – 4 No.s (300 KL, 750 KL, 1400 KL & 1500 KL)
  3.                Recycling Beds (Construction under Progress)
  4.                       Supervisory Quarters – 2 No.s
  • Intermediate Structures: Sumps             – 10 No.s
  1.         OHBRs               –  06 No.s
  2.         BPTs                  –  06 No.s
  3.         GLBRs                –  01 No.s
  4.         Pump Houses    –  09 No.s     

Pipeline Details:  

Total 1803.36 KMs pipe line of various types and dia meters was laid to connect and supply of water to all the rural and urban habitations under Palair Warangal segment of Mahabubabad district.

Bulk supply Status of Educational Institutions:   

Bulk supply connections were given to 78 Schools out of total 80 Schools and the remaining are pending due to lack of storage tanks at schools.

 

STAFF DETAILS  OF OFFICE OF EXECUTIVE ENGINNER MISSION BHAGIRATHA GRID DIVISION MAHABUBABAD 

S.No

Name of Officer

Designation

Head Quarter/Office

Mobile No

1

A.Surender

Executive Engineer

EE MB Grid  Divn. Mahaubabad

9100122261

2

N.Vamshi

Asst Executive Engineer

EE MB Grid  Divn. Mahaubabad

7995660591

3

V.Ravali

Asst Executive Engineer

EE MB Grid  Divn. Mahaubabad

7995660602

4

B.Surya

Dy Executive Engineer

Mahabubabad Sub Division

9100120488

5

CH. Hareesh

Asst Executive Engineer

Mahabubabad Mandal

7995660593

6

M.Nagaraju

Asst Executive Engineer

Gudur Mandal

7995660592

7

P.Suman

Asst Executive Engineer

Nellikudur Mandal

7995660596

8

N. Rajender

Asst Executive Engineer

Kesamudram Mandal

7995660594

9

M.Pradeep Kumar

Dy Executive Engineer

Maripeda Grid  Sub Division

9100120489

10

A.Shiva Prasad

Asst Executive Engineer

Peddavangara Mandal

7995660590

11

C. Nishank

Asst Executive Engineer

Thorrur Mandal

7995660595

12

N.Rakesh

Asst Executive Engineer

Maripeda Mandal

7995660811

Chinna Gudur Mandal

Narsimhulapet Mandal

Danthalapalle Mandal

13

B.Hanumanthu

Asst Executive Engineer

Korivi Mandal

7995660162

Dornakal Mandal

14

Mahammad Masood Ali Abid

Superintendent

EE MB Grid  Divn. Mahaubabad

7995660600

15

V. Anil Kumar

Sr. Assistant

Maripeda Grid  Sub Division

9949939199

16

B.Abhishek

Jr.Assistant

EE MB Grid  Divn. Mahaubabad

8686781262


Mission Bhagiratha Grid PPT (1)